Council adopted the Jetty4Shores Concept Plan, implementation plan and preliminary budget estimates at its Ordinary Meeting on 24 October 2013.
These plans were developed by a project team consisting of Coffs Harbour City Council, representatives from Crown Lands and a Community Reference Group. An extensive three-month exhibition was held from May to August 2013. A total of 1348 submissions were received in response to the exhibition.
Stage 1, the Jetty Walkway, was officially opened on 25 October 2015. The Walkway is a five-metre wide decorative concrete shared pathway/cycleway, which tells the story of our Aboriginal and European heritage, the Jetty structure and the industrial use of the Foreshores. Construction of 60-space car park was finished in early November 2016.
Stages 2-4 of the Jetty4Shores Project were officially opened on 30 October 2017.
These works comprised:
The detailed design documents for Stages 2 - 4 can be viewed below