Woolgoolga Water Reclamation Plant

A major upgrade of the Woolgoolga Reclamation Plant (WRP) to ensure a higher standard of water treatment and additional capacity to deal with extra sewerage flows from Mullaway and Arrawarra began in February 2004 and was completed 12 months later, at a total cost of $16 million.

Woolgoolga Water Reclamation Plant picture

The Woolgoolga Water Reclamation Plan was officially opened by Coffs Harbour Mayor, Councillor Keith Rhoades, and Clean Up Australia Chairman and founder, Ian Kiernan AO, on 11 March 2005.

The Woolgoolga WRP system serves Sandy Beach, Woolgoolga and Safety Beach. Work to connect Arrawarra and Mullaway to the sewerage system began in March 2005, and residents in this area will be able to plan for connection to the new system by the end of 2005.

The completion of the upgrade meant that the outfall to Willis Creek at Woolgoolga adjacent to Flat Top Rock could be decommissioned.

Preparation works begin

 

 < Preparation works begin, March 2004

                        

Construction of the sequence batch reactor, May 2004 >

Formwork for pump station

Testing for water leaks Woopi SBR tank

< Leak testing of tank's plastic liner, June 2004   

 


First concrete pour for the floor of the SBR, June 2004>

SBR Tank concrete pour

WRP aerial progress photo

 

 

 < Aerial photo of works in progress, June 2004

 




View of works from existing inlet works, July 2004>

View of works, July 2004

Progress of the destilling chamber July 2004

 

 

<Progress of works on the distilling chamber, July 2004

 

 

SBR Tank nearing completion, August 2004>

SBR Tank nearing completion
Completed SBR tank

 

< Final water testing of the completed SBR tank, August 2004

 

 

Testing of one of three surface mechanical aerators, August 2004>

Surface mechanical aerators
Aerial of WRP Progress Sept 2004

 

< SBR 2 is in operation and upgrading of SBR 1 is in progress, September 2004

 


Coffs Harbour Sewerage Strategy Community Advisory Group site visit, November 2004 >

Sewerage Strategy CAG visiting Woolgoolga WRP
Woolgoolga Water Reclamation Plant from the Air

 

< Construction of all major tanks and buildings was completed in December 2004

 

Alliance LogoCoffs Harbour City Council undertook this project as an alliance contract between GHD, Abigroup and Aquatec Maxcon. The WRP Alliance team worked together on the design from August 2003.

The construction works were designed to have a minimal impact on surrounding residents. Residents were informed of different stages of the construction through direct mail box drops or articles in the local Woolgoolga Advertiser.

For further information, please contact Council on (02) 6648 4403.

                                                                                                        
Visual Element

Visual Element Back To Top

Angle image Angle image Spacer Element Angle image Angle image Spacer Element Angle image Angle image Spacer Element Angle image Angle image Spacer Element Spacer Element
Publications & Reports Publications & Reports Learning Centre Learning Centre Community Directory Community Directory
Forms & Applications Forms & Applications Media Centre Media Centre Creative Directory Creative Directory Community Forums Community Forums