Construction of the new Coffs Harbour Water Reclamation Plant began in November 2006. The new $96 million plant is located adjacent to the existing sewerage plant between Howard Street and Christmas Bells Road.
![]() |
![]() |
|
| Pumps have been installed to distribute reclaimed water for a wide range of users including nurseries, sports grounds, schools, and the race course (photo February 3, 2009). | Part of the new Water Reclamation Plant, including the oxidation ditches, switchrooms, clarifiers, UV filtering, sludge building, secondary aerobic chambers and anaerobic reactors (photo January 30, 2009). | |
![]() |
![]() |
|
| Reclaimed water is used for testing of clarifiers one and two (photo February 3, 2009). | Oxidation ditch number one is also tested using relaimed water (photo February 3, 2009). | |
![]() |
![]() |
|
The sludge building (left) is now almost complete (photo Nov 21, 2008). |
The sludge thickener and centrifuge are now installed (photo Nov 21, 2008). |
|
![]() |
![]() |
|
Clarifier one is filled with water to undergo hydrostatic testing (photo Nov 21, 2008). |
Secondary aerobic chamber two is now being tested (photo Nov 21, 2008). |
|
![]() |
![]() |
|
Handrail construction begins on clarifier number one (photo June 26, 2008). |
The pump station for discharge of excess reclaimed water through the Deep Sea Release (photo June 26, 2008). |
|
![]() |
![]() |
|
Tilt-up wall panel construction begins for the new sludge building (photo June 26, 2008). |
Assembly of motor control centres in switch room one (photo June 26, 2008). |
|
![]() |
![]() |
|
Anaerobic reactors (foreground), with construction continuing on the pump station in the background (photo April 18, 2008). |
Clarifier number one (left), with oxidation ditch number one in the centre, and the pump station building pictured to the right (photo April 18, 2008). |
|
![]() |
![]() |
|
Oxidation ditch number two under construction (photo April 18, 2008). |
The filter block begins to take shape (photo April 18, 2008). |
|
![]() |
![]() |
|
The exterior of the main control building nears completion (photo April 18, 2008). |
Plant technician Ross Waugh inspects switch room number one (photo April 18, 2008). |
|
![]() |
![]() |
|
A section of the Inlet Works (photo April 18, 2008). |
Inlet pipes completed and awaiting connection (photo April 18, 2008). |
|
![]() |
![]() |
|
Clarifier number one begins to take shape (photo Jan 25 2008). |
Clarifier number two construction is well advanced (photo Jan 25 2008). |
|
![]() |
![]() |
|
The new Water Reclamation Plant's control building and switchroom under construction (photo Jan 25 2008). |
Anaerobic reactors under construction (photo Jan 25 2008). |
|
![]() |
![]() |
|
Councillors and staff on a site inspection of the oxidation tank, at the testing stage (photo 7 Nov 2007). |
Construction of the clarifier at the new Water Reclamation Plant (photo Coffs Infrastructure Alliance, Oct 2007). |
|
![]() |
![]() |
|
Concrete walls were constructed in August/September 2007.
|
This concrete pour was completed early September 2007. |
|
![]() |
|
|
Work is progressing well at the site of the Coffs Harbour Water Reclamation Plant (July 2007).
|
440m³ of concrete was poured as part of the construction of one of the WRP's oxidation tanks(July 2007). |
|
![]() |
|
|
Alliance staff working on the concrete pour |