Progress of Works + Photos
Work on the first stretch of the Hogbin Drive Extension (Albany Street to Harbour Drive) began in April 2006, starting with the relocation of services such as water, sewerage and electricity.
Earthworks for the road corridor between the Albany Street roundabout and Harbour Drive, and work on the construction of a roundabout on Harbour Drive, adjacent to Orara Street, began in August 2006.
The first section of the Hogbin Drive Extension (Harbour Drive roundabout to Albany Street roundabout) and the new roundabout on Harbour Drive both opened to traffic on 5 April 2007.
Work is continuing on the construction of the sections of road between the Harbour Drive roundabout and the bridge, and the northern section between the bridge and Orlando Street. Completion of these sections is expected in early 2008.
Information & photos of the bridge works can be found here.
![]() |
![]() |
Southern view from Orlando Street Roundabout, showing footpath works and the noise barriers (photo 1 Feb 2008) |
Landscaping works begin on the northern section of the Hogbin Drive Extension, near Orlando Street Roundabout (photo 1 Feb 2008) |
![]() |
![]() |
The pedestrian refuge and crossing midway between the new Bangalor Bridge and the Orlando Street Roundabout. Koala fencing shown in the background (photo 1 Feb 2008) |
The intersection of Hogbin Drive and Watsonia Avenue. Guttering is completed, and light poles have been installed (photo 1 Feb 2008) |
![]() |
![]() |
Wet weather in early November has delayed construction of the northern section of the Hogbin Drive Extension (photo 7 Nov 2007)
|
Hogbin Drive Extension north of Bangalor Bridge towards Orlando Street (photo 7 Nov 2007)
|
![]() |
![]() |
Perspective south towards Bangalor Bridge, from near Orlando Street (photo 7 Nov 2007) |
The northern extremity of the new Hogbin Drive Extension works, near the Orlando Street roundabout (photo 7 Nov 2007) |
![]() |
![]() |
Construction of the earth embankments that will form the base on which the road will be laid is in full swing at the northern section of the road, between the new bridge and Orlando Street (photo 26 Sept 2007)
|
Work on the section of the Hogbin Drive Extension north of the new bridge is progressing well. This will eventually link up with the Orlando Street roundabout (photo 24 Aug 2007)
|
![]() |
![]() |
Construction of the section of road between the bridge and Harbour Drive is well underway, with soundwalls also already installed (photo 24 August 2007)
|
Fauna underpass being built beneath the new road just north of the bridge over Coffs Creek to allow wildlife to cross the road safely (photo 12 July 2007)
|
![]() |
![]() |
With the new bridge over Coffs Creek completed, the section of road between the bridge and the Harbour Dr roundabout is now under construction (July 2007) |
The first new section of Hogbin Drive that opened to the public on 5 April 2007 - between Albany St roundabout and new Harbour Dr roundabout (photo June 2007)
|
![]() |
![]() |
View of the road corridor to the north of the new bridge over Coffs Creek (Feb 07)
|
View of the road corridor to the south of the new bridge over Coffs Creek (Feb 07)
|
![]() |
![]() |
Drainage works for the north side of the roundabout (Jan 2007) |
The southside of the roundabout was completed in December 2006 (photo Jan 2007)
|
![]() |
![]() |
The roundabout is taking shape (18 Oct 2006) |
Concrete being poured for the roundabout base (18 Oct 2006)
|
![]() |
![]() |
Road construction site visit by local Federal Member Luke Hartsuyker (orange vest), Councillors and staff (3 Oct 2006)
|
Site visit at cleared area on the south bank of Coffs Creek, ready for bridge works (3 Oct 2006) |
![]() |
![]() |
Foundation excavations for roundabout |
Wet weather has slowed the roundabout works schedule (27 Sept 2006)
|
![]() |
![]() |
The new road is taking shape
|
Victoria Street works
|
![]() |
![]() |
Council staff are running the works |
Looking north to Coffs Creek
|
![]() |
![]() |
The section of the Hogbin Drive extension from the Albany Street roundabout to Harbour Drive is rapidly progressing (early Sept 2006)
|
Works on the new Harbour Drive roundabout have required cooperation and the patience of motorists (early Sept 2006)
|
































